Glossary of elastomer processing
PPAP sampling (Level 1 to 3), Production Part Approval Process
PPAP sampling (Production Part Approval Process) is the automotive industry's series release process for validating components and processes. For sealing rings, moulded articles and flat seals, PPAP provides evidence that the drawing, material, process capability and documentation meet the customer's requirements.
PPAP is a customer-driven verification process (AIAG manual) that ensures series products can be manufactured reproducibly to specification. The result is part approval via the PSW, Part Submission Warrant (sample approval).
| PPAP level | Brief description | Typical use | Submission to the customer |
|---|---|---|---|
| Level 1 | PSW (warrant), all other evidence remains with the supplier | Low risk, standard/catalogue parts, resubmission without changes | PSW + label/sample label if required |
| Level 2 | PSW + limited supporting data | Moderate risk, few critical characteristics | PSW, product-related documents (e.g. dimensional report, material tests) + 1 to 3 sample parts |
| Level 3 | PSW + complete supporting data | New parts, dimensionally critical components, safety/regulatory requirements | PSW, complete PPAP package + sample parts + master sample/gauge evidence |
Note: levels 4/5 also exist (customer-specific or on-site audit); in the sealing sector, levels 1 to 3 predominate.
| # | Element | Content / example for seals | Submission (L1/L2/L3) |
|---|---|---|---|
| 1 | Design Record | Drawing with tolerances, material code, critical characteristics (✱/CC/SC) | - / ✓ / ✓ |
| 2 | ECNs | Approved change levels | - / ✓ / ✓ |
| 3 | Customer Engineering Approval | Advance approvals, if required | - / (✓) / (✓) |
| 4 | DFMEA | For customer-owned design, otherwise “not applicable” | - / - / (✓) |
| 5 | Process Flow Diagram | Goods receipt → compound/sheet → cutting/punching/moulding → QA → dispatch | - / ✓ / ✓ |
| 6 | PFMEA | Risks: dimensional deviation, hardness/compression set behaviour, flash, mix-ups | - / ✓ / ✓ |
| 7 | Control Plan | Dimensional/hardness checks, visual inspection, traceability | - / ✓ / ✓ |
| 8 | MSA | Measurement system analysis (e.g. Shore A, diameter/profile) | - / (✓) / ✓ |
| 9 | Dimensional Results | Dimensional report on n parts (critical characteristics 100% or n = customer-specific) | - / ✓ / ✓ |
| 10 | Material / Performance Tests | Material testing, media resistance, KTW-BWGL/WRAS/FDA/UL 94 if applicable | - / ✓ / ✓ |
| 11 | Initial Process Studies | SPC/Cp Cpk for critical dimensions (target usually ≥ 1.33/1.67) | - / (✓) / ✓ |
| 12 | Qualified Laboratory | Accreditation evidence for test laboratories | - / (✓) / ✓ |
| 13 | Appearance Approval | AAR, for parts where appearance matters | - / - / (✓) |
| 14 | Sample Production Parts | Sample parts manufactured with series parameters | - / ✓ / ✓ |
| 15 | Master Sample | Reference part, retained by the supplier | - / - / (✓) |
| 16 | Checking Aids | Gauges/test fixtures, calibrations | - / - / (✓) |
| 17 | Packaging Approval | Approved packaging/labels/traceability | - / (✓) / ✓ |
| 18 | PSW, Warrant | Approval document (with deviations, if any) | ✓ / ✓ / ✓ |
Exact submission requirements according to customer-specific requirements (CSR). ”(✓)” = frequently required.
-
Kick-off & CSR check: clarify customer requirements (level, sample size, labels, IMDS, special approvals).
-
Process/inspection planning: define flow, PFMEA, control plan, test equipment/gauges.
-
Sample production: components made with series parameters; carry out tests/analyses (dimensions, hardness, function, media/fire behaviour if applicable).
-
Documentation package: consolidate the PPAP documents according to the level; prepare the PSW.
-
Submission & review: digital submission, clarification of queries, final approval.
Practical tip: define critical dimensions early (drawing/CC/SC) and validate the measurement concept (MSA/SPC) before sample production. This saves iteration loops.
| Aspect | PPAP (AIAG) | VDA 2 (PPF) |
|---|---|---|
| Approval document | PSW (Part Submission Warrant) | PPF forms (e.g. VDA 2 annex) |
| Levels | Level 1 to 5 | Submission levels A-D (customer-specific) |
| Critical characteristics | SC/CC, customer-specific symbols | Special characteristics, VDA conventions |
| Relevance for seals | Widely used internationally | Very common in the D-A-CH automotive sector |
-
How many parts do I need for the dimensional report? This is defined by the customer (CSR). Often 5 to 30 parts, critical characteristics 100% if required.
-
Does IMDS have to be submitted? If required by the customer (especially in automotive). We supply IMDS entries on request.
-
Does PPAP approval remain valid after a change of material? Changes to formulation, hardness or colour must be notified and often require resubmission.
We prepare PPAP packages to level 1 to 3, including dimensional reports, MSA/SPC, material and functional tests and PSW submission.
Questions about this term?
Our technical advice
Do you have a specific application or a question about elastomer processing? Talk to us, we will help you with material, process and approval.